The expertise of Centrilift staff comes from many years of dismantling, removing and
installing plant for major companies in the process and packaging industries.
We are able to offer a complete service working in conjunction with
Centriplant who are able to broker sales of plant direct from site.
We are proud to have been associated with:
POWELL DUFFRYN
Dismantle and dispose of a complete bulk liquid
storage terminal located on the Thames Estuary.
This project also included:
- Relocation of 2 x 620 ton and 2 x 350 ton vertical bulk storage tanks by sea from Thames Estuary to Southampton
- Dismantle a 7 birth jetty to slab level
GLAXO SMITHKLINE
Dismantle and remove 8 x 136 cubic metre gas tanks
all associated pipework and gantries.
Transport to our tank storage facility in Guildford
Dismantle and remove 3 x Nauta mixers from
powder mixing area at manufacturing site
CANTERBURY MILLS
Load and transport 3 x 90,000 litre dairy silos weighing
12 tons each together with walkways, ladders and CIP
equipment to new location. Offload and position
BACARDI MARTINI
Removal of Bevco warmer from site
and re-allignment of Krones labeller
BRITVIC
Removal of de-palletiser and twin bowl bottle sorter
PURA FOODS
De commission, dismantle and remove
complete edible oil process plant in London
site clearance ready for hand over to developers
|
|
|
A Division of Centriplant Rebuilds & Tank Co Ltd
Littlemead Industrial Estate, Alfold Road, Cranleigh, Surrey, GU6 8ND, England
Tel: +44 (0)1483 271507 Fax: +44 (0)1483 278183
E-mail: centrilift@centriplant.co.uk
See our other Division CENTRIPLANT REBUILDS & TANK CO LTD ~ www.centriplant.co.uk
|